New City Hall and Library
UPDATE ON CITY HALL/LIBRARY COMPLEX
May 27, 2008

City
Hall Complex Construction as viewed from State Highway 3
May 28, 2008.
Possible design modifications were presented to the City Council by Mr. Bill
Hall of Hall, Barnum & Lucchesi at several different Council meetings during
January, February and March of 2008. While incorporating most of the possible
design modifications to bring the Project into budget, the one design
modification that the Council chose not to approve was to go with a low-slope
roof for the buildings. Even with the design modifications that were
incorporated, the Project exceeds the original construction cost by $1.5
million. At the April 22, 2008 meeting, the Council allocated $400,000 of the
unreserved/undesignated fund balance from the 2006-2007 Fiscal Year to the
Capital Projects Fund specifically to fund a portion of the excess construction
costs. The City also submitted a request for additional funds of approximately
$316,000 to Galveston County Water Control and Improvement District No. 1;
however, Galveston County Water Control and Improvement District No. 1 denied
the City’s request at its May 12, 2008 Board meeting. At this time, the City
anticipates that it will be able to fund the excess construction costs through
unexpended fund balance for Fiscal Years 2007-2008 and 2008-2009. City staff is
also working diligently to identify any other potential funding sources for the
excess construction costs.
On March 11, 2008, the Council authorized the City Administrator to proceed with
issuing a Request for Proposals to retain a Construction Manager at Risk for the
project. The Request for Proposals was issued by the City on March 19, 2008. The
proposal opening occurred on April 3, 2008, with only one proposal being
submitted by Durotech. The RPF was awarded to Durotech by the Council at the
April 8 Council meeting, and City staff was instructed to proceed with
negotiation of a contract. A contract with Durotech was approved at the April
22, 2008 Council meeting.
Between April 22, and May 13, 2008, temporary fencing was erected around the
construction site and a construction trailer was located on the site. Demolition
of the old foundations for the former muffler shop and old houses and
underground utilities that were on the site was conducted the week of May 12,
2008. A building permit for the Project was issued by the City on May 27, 2008,
and a ground breaking ceremony is scheduled for May 29, 2008 at 4:00 pm.
Watch for updates as the Project progresses.
|

|
|
 |