UPDATE ON CITY HALL PROJECT

October 14, 2008

 

Work remains on schedule despite Hurricane Ike delay of approximately one week – minor damage to site (downed trees and fencing) - currently scheduled for substantial completion by April 2009.

  • Structural steel set for both City Hall and Library

  • Bracing for decking has begun on City Hall and Library

  • In the next few weeks, the following work is scheduled:

    • Complete detailing

    • Start metal decking

    • Exterior studs

    • Roof blocking

    • Exterior sheathing

    • Exterior frames

    • Brick delivery

    • Interior metal studs

  • Work is occurring concurrently on City Hall and Library with use of two crews

City Attorney working on Consent to Encroachment related to law office on FM 517.

Girls Scouts scheduled for a site visit on October 10 to earn their engineering badge.

 

 

City Hall Complex Construction as viewed from State Highway 3

October 14, 2008.  

 


New Library Construction as viewed from State Highway 3

October 14, 2008. 


 