The
project is on schedule for substantial completion in April 2009.
-
The
steel erector is completing the welding of the roof decking for both City
Hall and Library.
-
The
exterior wall studs are being installed on both City Hall and Library.
-
The
HVAC duct work and the electrical conduits are being installed on both the
City Hall and Library.
-
Staff
still in discussions with the architect and electrical engineer regarding
the installation of a transfer switch for an emergency generator.
-
West
side parking and driveways have been poured.
-
Brick
scheduled to begin this week.
-
Roof
panels scheduled to begin this week.
-
City
staff is meeting with different vendors for telephone systems.
-
City
Administrator working on quotes for signage.